South Oswego-Tar Hill

Construction Updates

South Oswego-Tar Hill

Construction Updates

Return to project page

Contact National Grid if you have questions related to this project.

Two-Week Schedule:

Week of September 28, 2026

Scriba

Maiden Lane Substation and Laydown Yard:

  • Crews continue foundation work, including drilling and concrete pad installation for substation equipment.
  • Installment of topsoil continues as part of site grading activities.

County Route 51A Building Removals:

  • Building removal work has concluded.
  • Ground restoration activities continue.

Week of October 5, 2026

Scriba

Maiden Lane Substation and Laydown Yard:

  • Crews continue foundation work, including drilling and concrete pad installation for substation equipment.
  • Installment of topsoil continues as part of site grading activities.

County Route 51A Building Removals:

  • Building removal work has concluded.
  • Ground restoration activities continue.