Contact National Grid if you have questions related to this project.
Two-Week Schedule:
Week of October 26, 2026
Town of Scriba
Maiden Lane Substation and Laydown Yard:
- Crews continue foundation work, including drilling and concrete pad installation for substation equipment.
- Grounding and backfilling continue throughout the substation site.
- Control house assembly continues.
County Route 51A Laydown Yard:
- Crews are mobilizing to begin construction of the laydown Yard.
Town of Mexico
County Route 16 Laydown Yard:
- Crews are mobilizing to begin construction of the laydown Yard.
Week of November 2, 2026
Town of Scriba
Maiden Lane Substation and Laydown Yard:
- Crews continue foundation work, including drilling and concrete pad installation for substation equipment.
- Grounding and backfilling continue throughout the substation site.
- Control house assembly continues.
County Route 51A Laydown Yard:
- Crews continue developing the laydown yard to support upcoming construction activities.
Town of Mexico
County Route 16 Laydown Yard:
- Crews continue developing the laydown yard to support upcoming construction activities.