Contact National Grid if you have questions related to this project.
Two-Week Schedule:
Week of September 14, 2026
Scriba
Maiden Lane Substation and Laydown Yard:
- Crews continue foundation work, including drilling and concrete pad installation for substation equipment.
- Assembly of electrical equipment to prepare for installation continues.
County Route 51A Building Removal:
- Crews continue demolition activities.
- Crews will stabilize the ground area where the structures were demolished.
Week of September 21, 2026
Scriba
Maiden Lane Substation and Laydown Yard:
- Crews continue foundation work, including drilling and concrete pad installation for substation equipment.
- Assembly of electrical equipment to prepare for installation continues.
County Route 51A Building Removal:
- Crews continue demolition activities.
- Crews will stabilize the ground area where the structures were demolished.