Contact National Grid if you have questions related to this project.
Two-Week Schedule:
Week of September 28, 2026
Scriba
Maiden Lane Substation and Laydown Yard:
- Crews continue foundation work, including drilling and concrete pad installation for substation equipment.
- Installment of topsoil continues as part of site grading activities.
County Route 51A Building Removals:
- Building removal work has concluded.
- Ground restoration activities continue.
Week of October 5, 2026
Scriba
Maiden Lane Substation and Laydown Yard:
- Crews continue foundation work, including drilling and concrete pad installation for substation equipment.
- Installment of topsoil continues as part of site grading activities.
County Route 51A Building Removals:
- Building removal work has concluded.
- Ground restoration activities continue.