Mortimer-Golah

Western New York

National Grid’s Mortimer-Golah project includes rebuilding nearly 20 miles of transmission lines in Monroe County, and upgrades to one substation.

Mortimer-Golah

Western New York

National Grid’s Mortimer-Golah project includes rebuilding nearly 20 miles of transmission lines in Monroe County, and upgrades to one substation.

Project Quick Facts

  • The Mortimer-Golah transmission lines are located in Monroe County and travels through the towns of Brighton, Henrietta and Rush.
  • The project involves rebuilding approximately 9.6 miles of the 115kv Mortimer-Golah Line 110 from the Mortimer substation in Brighton to the Golah substation in Rush, and rebuilding and upgrading – from 69kv to 115kv – approximately 10.1 miles of the Mortimer-Golah Line 109 from the Mortimer substation to the Golah substation.
  • National Grid will also rebuild the Golah substation to support the project.
  • Also included are technologies to improve response time and decrease maintenance costs.

Current Activities

National Grid is in the fieldwork and design phase. We are currently reviewing transmission corridors and collecting information for project design. This includes environmental, cultural and other field studies such as land survey and geotechnical studies (soil borings).

Permitting and Participation

This project will require Article VII permitting to proceed. For more information about permitting, please see our Project FAQ page.

The permitting process includes opportunities for public involvement and comment from permitting through construction. To contact National Grid with a question or comment, you may reach us by phone at 833-644-6524 or [email protected].

Once National Grid submits its Article VII Application to the Public Service Commission, interested persons who wish to participate as parties in this case may file for party status. This may be done through the Commission’s website. Further instructions will become available here once the Application is submitted.

Schedule

  • Field Studies and Design: 2023-2024
  • Permitting: 2024-2026
  • Anticipated Construction Start: 2026
  • Anticipated Construction Completion: 2029