Inghams-Rotterdam

Eastern New York

National Grid’s Inghams-Rotterdam project includes rebuilding nearly 51 miles of transmission lines in four counties and upgrades to one substation.

Inghams-Rotterdam

Eastern New York

National Grid’s Inghams-Rotterdam project includes rebuilding nearly 51 miles of transmission lines in four counties and upgrades to one substation.

Project Quick Facts

  • Inghams-Rotterdam serves four counties: Fulton, Herkimer, Montgomery, and Schenectady.
  • The project travels through the city of Johnstown, and towns of Amsterdam, Canajoharie, Ephratah, Florida, Johnstown, Manheim, Minden, Mohawk, Oppenheim, Palatine, Perth, St. Johnsville, Princetown, and Rotterdam.
  • The project will replace existing 115kV wire and structures in the right-of-way. Additional easements may be needed for the construction and operation of the line.
  • Also included are access roads upgrades, and technologies to improve response time and decrease maintenance costs.
  • The project will include the addition of a new substation at Saltsman Road in Ephratah. No additional easements are needed for the construction and operation of the new substation. 

Agriculture Survey

Farming is a time-honored tradition in New York and an important part of the economy. Much of the lands surrounding the existing Inghams-Rotterdam transmission corridor in the Mohawk Valley are used for agricultural purposes. 

As part of National Grid’s ongoing outreach efforts to better understand the agricultural activities taking place on adjacent lands, we are conducting a survey to gather information from farm operators. This information will help inform construction plans for the project. Our team is committed to working with area farmers to minimize disruption to agricultural lands during construction activity to the extent possible. 

We would appreciate you taking the time to complete the survey, located at the link below. If there are active leased farming operations on your land, we ask that you include the lessee’s contact information. If you have any questions or difficulty filling out the survey, please contact our team at 877-551-4743 or [email protected].

Click here to access the Agricultural Survey

Current Activities

The project received approval of its Article VII Permit from the New York Public Service Commission on May 15, 2026. Environmental Management and Construction Plans will be submitted in the coming weeks.

Construction‑related permitting and preparations for a project marshalling yard in St. Johnsville is actively underway. Permitting work will continue as each transmission line segment approaches its scheduled construction window.

Construction of Segment 6: Inghams to St. Johnsville began on June 8, 2026. Early activities include right‑of‑way staking, mowing and tree clearing, and installation of access roads. Construction on this segment will continue through January 2027.

Planning and design efforts continue across the remaining transmission line segments. This includes detailed reviews of transmission corridors and field walkdowns with National Grid staff and contractors to support final design, access planning, and construction preparation.

Permitting and Participation

This project requires both Article VII and Part 102 permitting to proceed. 

National Grid received its Article VII permit on May 15, 2026 for the Saltsman Road Substation and required line segments as part of case no. 25-T-0262. Part 102 permit applications for applicable line segments were submitted to the PSC in January 2026.

Article VII projects also require approvals of Environmental Management and Construction Plans. Those will be submitted to the PSC in the coming weeks.

For more information about permitting, please see our Project FAQ page.

Thank you to everyone that attended our open houses, either virtually or in person in Amsterdam, Canajoharie and St. Johnsville. We also thank those of you who attended the virtual public statement hearing conducted by the Public Service Commission on January 8, 2026.

You may always contact us with questions or comments at [email protected] or 877-551-4743.

 

Schedule

  • Construction Started: June 2026
  • Anticipated Construction Completion: Winter 2029-2030