Permitting and Participation
This project will require permitting under Part 102 of the New York State Codes, Rules and Regulations to proceed. National Grid submitted its permit application to the PSC on December 15, 2025. For more information about permitting, please see our Project FAQ page.
The permitting process includes opportunities for public involvement and comment from permitting through construction. To contact National Grid with a question or comment, you may reach us by phone at 716-508-2061 or [email protected].
Schedule
- Design & Permitting: Through Fall 2026
- Anticipated Construction Start: Fall 2026
- Anticipated Construction End: 2027