Oneida-Porter

Oneida County Transmission Upgrade (CGPP)

The Oneida-Porter Transmission Rebuild Project is a segment of National Grid's Oneida County Transmission Upgrade proposal.

Oneida-Porter

Oneida County Transmission Upgrade (CGPP)

The Oneida-Porter Transmission Rebuild Project is a segment of National Grid's Oneida County Transmission Upgrade proposal.

Project Quick Facts

  • The Oneida-Porter 115kV Transmission Rebuild Project will rebuild approximately 21.5 miles of 115kV transmission line in Oneida County. 
  • The project travels through the towns of Marcy, Vernon, Verona, Westmoreland and Whitestown.
  • The project will replace an existing 115kV double circuit wire and structures in the right-of-way with two 115kV single circuit lines to meet updated requirements. Additional easements may be needed for the construction and operation of the line.
  • National Grid will construct a new substation in Walesville, and upgrade substations in Marcy and Oneida.
  • Also included are access roads upgrades, and technologies to improve response time and decrease maintenance costs.
  • This project is proposed as part of National Grid's Oneida County Transmission Upgrade in CGPP Cycle One.

Public Comment

 

Members of the public are welcome to contact National Grid with questions or concerns by calling 844-324-3588 or emailing [email protected].

Permitting and Participation

This project will require Article VIII permitting to proceed. For more information about permitting, please see our Project FAQ page.

Schedule

Survey and Environmental Review: Through 2026
Design and Engineering: 2027-2030
Anticipated Construction Start: 2030