Contact National Grid if you have questions related to this project.
Week of September 28th, 2026
- Building access and work pads along State Highway 72 and 11B in Parishville
- Installing construction entrance near State Highway 72 in Parishville
Week of October 5th, 2026
- Set top and transfer near county route 47 in Parishville
- Establish wire-pulling sites
- Install conductor blocks
- Pull overhead shield wire, optical ground wire, and conductor
- Sag and clip overhead shield wire, optical ground wire, and conductor