Contact National Grid if you have questions related to this project.
Week of September 14th, 2026
- Wire pulling along Benson Road and West Parishville Road.
- Staking in the right-of-way and wetlands along State Highway 72 in Parishville.
- Building access and work pads along Lenny Road and Russell Turnpike in Parishville.
Week of September 21st, 2026
- Wire pulling and installing conductor blocks along Benson Road, West Parishville Road and Pumpkin Hill Road
- Staking in the right-of-way and wetlands along State Highway 72 and 11B in Parishville
- Building access and work pads along State Highway 72 and 11B in Parishville
- Installing construction entrance near State Highway 72 in Parishville