Colton-Nicholville

Construction Updates

Colton-Nicholville

Construction Updates

Return to project page

Contact National Grid if you have questions related to this project.

Town of Parishville
Week of November 9th, 2026

  • Crews will continue wire pulling, sagging, and clipping activities along State Highway 72.
  • Crews will continue removing construction mats and restoring previously completed work areas.
  • Tree clearing activities will continue within designated project work areas.

Town of Parishville
Week of November 16th, 2026

  • Crews will continue wire pulling, sagging, and clipping activities along State Highway 72.
  • Crews will continue removing construction mats and restoring previously completed work areas along the transmission line corridor.
  • Tree clearing activities will continue within designated project work areas, including areas near Pumpkin Hill Road and State Highway 72.