Contact National Grid if you have questions related to this project.
Geotechnical investigations, including soil borings and ground penetrating radar, are ongoing.
Week of June 15, 2026
- Drilling for structures 24 through 38 along Rt 12 and Miller Road in Watertown through June 16
- Gravel and Matting for structures 53 through 58 along Perch Lake Road, White Road, Fisher Road in the Town of Brownville and Town of Watertown through June 12