Black River-Clay

Construction Updates

Black River-Clay

Construction Updates

Return to project page

Contact National Grid if you have questions related to this project.

Two-Week Schedule:
Staplin Creek Substation 

Town of Rutland
Week of October 12th, 2026

  • Continue parking area grading and site preparation activities.
  • Begin topsoil stripping within the control house area.
  • Start excavation for the control house foundation.
  • Receive construction materials and continue foundation preparation work.

Town of Rutland
Week of October 19th, 2026

  • Continue excavation and foundation construction for the control house.
  • Perform reinforcement steel installation and foundation preparation activities.
  • Begin control house foundation formwork.
  • Continue overall site grading and pad development activities.