Contact National Grid if you have questions related to this project.
Two-Week Schedule:
Staplin Creek Substation
Town of Rutland
Week of October 26th, 2026
- Crews will continue foundation reinforcement activities within the substation site.
- Foundation work will continue as construction progresses within the substation.
- Drill rig, casing, and tooling mobilization activities will continue as scheduled.
Town of Rutland
Week of November 2nd, 2026
- Crews will continue excavation and backfill activities within the substation site.
- Reinforcement tying for foundations will continue as construction progresses.
- Drill rig, casing, and tooling mobilization activities will continue in preparation for drilled shaft installation.