Contact National Grid if you have questions related to this project.
Two-Week Schedule:
Staplin Creek Substation
Town of Rutland
Week of November 16th, 2026
- Crews will continue excavation and backfill activities associated with temporary power installation within the substation site.
- Crews will continue reinforcement tying and formwork activities associated with the control house foundation.
- Installation of the perimeter swale and diaphragm will continue as construction progresses within the substation site.
- Crews are expected to begin drilled shaft installation, pending delivery of required materials.
Town of Rutland
Week of November 23rd, 2026
- Crews will continue weather-dependent drilled shaft installation activities within the substation site.
- Crews will begin topsoil stripping and excavation activities for the control house foundation.
- Construction activities will pause on Thanksgiving and the following day, November 26 and 27.