Two Week Lookahead:

Week of September 7, 2026

Croghan

Beaver River Substation and Taylorville Laydown Yard (Effly Falls Road):

  • Crews are mobilizing to the substation and laydown yard sites, including installation of parking, trailers, and material storage. 
  • Environmental protections are being installed.
  • Deliveries are coming to site.

Week of September 14, 2026

Croghan

Beaver River Substation and Taylorville Laydown Yard (Effly Falls Road):

  • Crews continue to mobilize to the substation and laydown yard sites, including installation of access roads, fencing, and environmental protections.