Beaver River-Porter

Construction Updates

Beaver River-Porter

Construction Updates

Return to project page

Contact National Grid if you have questions related to this project.

Two Week Lookahead:

Week of October 5, 2026

Croghan

Beaver River Substation and Taylorville Laydown Yard (Effly Falls Road):

  • Continue stripping topsoil at the substation

  • Continue tree clearing along station access road

  • Begin installing the main access road from Effley Falls to the Substation

  • Continue to set up laydown yard
     

Week of October 12, 2026

  • Continue to set up laydown yard
  • Continue tree clearing along station access road
  • Continue stripping and grading topsoil/subsoil inside substation