Two Week Lookahead:
Week of October 5, 2026
Croghan
Beaver River Substation and Taylorville Laydown Yard (Effly Falls Road):
-
Continue stripping topsoil at the substation
-
Continue tree clearing along station access road
-
Begin installing the main access road from Effley Falls to the Substation
-
Continue to set up laydown yard
Week of October 12, 2026
- Continue to set up laydown yard
- Continue tree clearing along station access road
- Continue stripping and grading topsoil/subsoil inside substation