Contact National Grid if you have questions related to this project.
Two Week Lookahead:
Week of November 16, 2026
Croghan
Beaver River Substation and Taylorville Laydown Yard (Effley Falls Road)
- Continue grading through the center of the substation. Plan to continue from the east to west side of the substation.
- Continue installing the South slope
- Continue shaping the driveways and install drainage features at the substation entrance
Week of November 23, 2026
- Continue grading along east side of the substation
-
Continue installing the east slope